Free Submittal Log Template for Construction (Excel and CSV)
A submittal log tracks every shop drawing, product data sheet and sample the specs require, from the date it is due from the subcontractor to the date it is approved and released for ordering. This free Excel template works backward from the date material must be on site, subtracting lead time and review time to give each submittal a submit-by date, then tracks review codes, ball in court and resubmittals automatically.
Download the template
- ExcelSubmittal log workbookExcel. Log, summary, lists and instructions. 42 KBDownload Submittal log workbook (Excel)
- CSVSubmittal log as CSVFor Google Sheets, Smartsheet or any import. 2 KBDownload Submittal log as CSV (CSV)
The example rows use a fictional project. Delete them and the template is ready for yours.
What's in the template
- 23 columns numbered by spec section, with revision tracking
- Submit-by date calculates from required-on-site date, lead time, reviewer days and GC review days
- Status and ball in court calculate from the dates and the action code
- Days in review and days to submit-by calculate from the status date
- Late items turn red. Items due within 14 days turn amber
- Summary sheet: not received, late, with reviewer, past review due, resubmit required, approved but not released
- Seven example lines from a fictional medical office building, including a resubmittal
- Opens in Excel, Google Sheets, Numbers and LibreOffice. Free, no email required
What a working submittal log looks like
Seven lines from a fictional medical office building, as of Nov 20, 2026. Two problems stand out. The air handling unit product data was due Oct 21 and has not arrived, so a 16-week lead time is already eating into the March delivery. The panelboards have been with the engineer for 39 days against a 14-day review.
| No. / rev | Description | Required on site | Lead (wks) | Submit by | Received | Review due | Code | Status | Ball in court | Days in review | Days to submit-by |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 03 30 00-001 R0 | Concrete mix designs | Sep 14, 2026 | 1 | Aug 25, 2026 | Aug 10, 2026 | Aug 21, 2026 | NET | Approved | GC (release) | 10 | |
| 05 12 00-001 R0 | Structural steel shop drawings | Nov 30, 2026 | 10 | Sep 2, 2026 | Aug 25, 2026 | Sep 11, 2026 | MCN | Approved | GC (release) | 17 | |
| 08 44 13-001 R0 | Curtain wall shop drawings and calcs | Feb 15, 2027 | 14 | Oct 21, 2026 | Oct 16, 2026 | Nov 2, 2026 | R&R | Resubmit required | Example Glazing | 18 | |
| 08 44 13-001 R1 | Curtain wall shop drawings and calcs (resubmittal) | Feb 15, 2027 | 14 | Oct 21, 2026 | Nov 16, 2026 | Dec 1, 2026 | With reviewer | Architect | 3 | ||
| 23 73 13-001 R0 | Air handling units AHU-1 to AHU-3 | Mar 1, 2027 | 16 | Oct 21, 2026 | Not received | Example Mechanical | -30 | ||||
| 26 24 16-001 R0 | Panelboards | Jan 18, 2027 | 12 | Oct 7, 2026 | Oct 9, 2026 | Oct 26, 2026 | With reviewer | MEP engineer | 39 | ||
| 09 51 13-001 R0 | Acoustical ceiling tile samples | Apr 5, 2027 | 6 | Feb 3, 2027 | Not received | Example Interiors | 75 |
How the submit-by date is calculated
A submittal is late long before the reviewer stamps it. The real deadline is the date the subcontractor has to send it to you so that review, fabrication and delivery still finish before the material is needed. The template calculates that date for every line:
Submit-by date = required on site − (lead time in weeks × 7) − reviewer days − GC review days
Take the curtain wall in the example. It must be on site Feb 15, 2027. Fabrication and delivery take 14 weeks (98 days), the architect has 14 days to review, and the GC allows 5 days to check the package first. Working back gives a submit-by date of Oct 21, 2026. The first submission arrived Oct 16, five days early, but it came back Revise and Resubmit. The resubmittal now has no float, which is why the GC asked the architect for a seven-day review.
Get the required-on-site date from the schedule activity that installs the material, and the lead time from the supplier, not from memory. Update both when the schedule or the quote changes. Days to submit-by turns negative the day a submittal becomes late, which is your signal to call the sub rather than wait for the next meeting.
What each column is for
| Column | What to enter | Why it matters |
|---|---|---|
| Submittal no. and rev | Spec section plus a sequence (08 44 13-001) and the revision number. | Spec-based numbers keep every submittal for a system together and match how reviewers file them. |
| Spec section, description, type | The section, a plain description, and product data, shop drawings, samples, mock-up and so on. | The specs list exactly which types each section requires. Build the log from them. |
| Sub / supplier and reviewer | Who prepares it and who reviews it: architect, structural or MEP engineer, owner, consultant. | Ball in court needs both names. |
| Required on site | The date the material must be on site to meet the schedule. | The anchor for the whole calculation. |
| Lead time, reviewer days, GC review days | Supplier lead time in weeks, the review period in the specs, and your own review time. | These set the submit-by date. Update them when quotes or specs change. |
| Submit-by date | Nothing. It calculates. | The date the sub must deliver the package to you. |
| Received, sent, returned | The three hand-off dates. | Status, ball in court, review due and days in review all come from these. |
| Review due | Nothing. It calculates from the date sent and reviewer days. | The date you can hold the reviewer to. |
| Action code | The reviewer's stamp: NET, MCN, R&R, REJ or FIO. | Decides whether it is approved or goes back to the sub. |
| Status and ball in court | Nothing. They calculate. | Not received, GC review, with reviewer, resubmit required or approved, and who owes the next move. |
| Days in review and days to submit-by | Nothing. They calculate. | Turn red and amber so late items are visible at a glance. |
| Released to order | Yes once the approved submittal is back with the sub and the order is placed. | Approval does not mean material is coming. This column closes that gap. |
Review action codes
Architects and engineers stamp submittals with an action. Wording varies, so match the Lists sheet to your reviewer's stamp. The template treats the codes this way:
| Code | Meaning | What happens next | Template status |
|---|---|---|---|
| NET | No exceptions taken | Release to the sub for fabrication or ordering. | Approved |
| MCN | Make corrections noted | Release, and the sub incorporates the noted corrections. No resubmittal unless the stamp asks for one. | Approved |
| R&R | Revise and resubmit | Back to the sub. Nothing is fabricated or ordered until the resubmittal is approved. | Resubmit required |
| REJ | Rejected | Back to the sub with a different product or approach. | Resubmit required |
| FIO | For information only | Filed. No review action required. | Approved |
Tracking resubmittals
Never overwrite a returned submittal with the new dates. Add a new line with the same number and the next revision: 08 44 13-001 Rev 0, then Rev 1. The log then shows how many cycles each package took and how much review time it used, which is the evidence you need if repeated rejections push a delivery.
Each revision gets its own received, sent and returned dates, so days in review and review due work per cycle. Filter on the submittal number to see the full history in one place.
How to run the log each week
Build the register before the first submittal arrives
Go through the spec sections and add a line for every required submittal. Enter required-on-site dates from the baseline schedule and lead times from the subcontractors.
Sort by days to submit-by
Red lines are late from the sub. Amber lines are due within 14 days. Call the long-lead items first.
Check what is with the reviewer
Filter status to With reviewer. Anything past review due is red. Send the reviewer one list, ordered by required-on-site date.
Process returns the same day
Enter the returned date and action code, send the stamped submittal to the sub, and add a revision line if it came back R&R or REJ.
Confirm releases
For approved items, confirm the sub placed the order and mark Released to order. Ask for a ship date on anything long lead.
Common submittal log mistakes
- Starting the log when the first package arrives. By then, long-lead items may already be late. Build it from the specs.
- Tracking only the reviewer's turnaround. The bigger risk is the sub's late submission, which only a submit-by date shows.
- Treating approval as delivery. An approved submittal has not been ordered until someone confirms it.
- Overwriting revisions. You lose the review history and the evidence of repeated rejections.
- Ignoring the GC review step. Packages that go straight to the architect incomplete come back R&R and cost a full cycle.
- Lead times from last year's job. Ask the supplier for a current quote, especially for switchgear, AHUs and curtain wall.
Submittal log, register and schedule
A submittal register is the list of every submittal the specs require. A submittal schedule adds the dates each one is due. A submittal log tracks each one as it moves through review. Many teams keep them separately and lose the thread between them. This template is all three in one sheet: build the register from the specs, the dates make it a schedule, and the hand-off columns make it a log.
Know what is late before the meeting
A Clevis bot can keep a working submittal list from the specs, schedule and correspondence you give it access to. It can show which packages are owed by subcontractors and which are with reviewers, so each chase asks the right party for the right thing.
Ask it which submittals are tied to work in the next three weeks, or which approved items have no confirmed order, and it will cite the record behind each answer. It can produce the list as an Excel file and draft the follow-ups. You approve anything before it is sent, and a review status in Clevis is never treated as proof that material was ordered or shipped.
Frequently asked questions
What is a submittal log in construction?
A submittal log is a list of every shop drawing, product data sheet, sample and other submittal the specifications require, with the dates each one is due, received, sent for review and returned, the review action, and who owes the next step. The general contractor uses it to make sure materials are approved and ordered in time for the schedule.
What should a submittal log include?
Submittal number and revision, spec section, description, type, subcontractor, reviewer, required-on-site date, lead time, review time, submit-by date, dates received, sent and returned, review due date, action code, status, ball in court and whether the item has been released for ordering.
How do you calculate when a submittal is due?
Start from the date the material must be on site. Subtract the supplier's lead time, the reviewer's turnaround from the specs and your own GC review time. The result is the date the subcontractor must deliver the submittal to you. This template calculates it for every line.
What is the difference between a submittal log and a submittal register?
The register is the master list of required submittals, usually built from the spec sections at the start of the job. The log tracks each submittal through review. In this template they are the same sheet: start with the register lines and fill in the dates as each package moves.
How should resubmittals be tracked?
Add a new line with the same submittal number and the next revision number instead of overwriting the original. Each revision keeps its own dates and action code, so the log shows every review cycle.
What do NET, MCN and R&R mean on a submittal?
They are common review actions. NET means no exceptions taken. MCN means make corrections noted, so the work can proceed with the corrections. R&R means revise and resubmit, so nothing is released until a corrected package is approved. Wording varies by firm, so match the codes to your reviewer's stamp.
Who is responsible for the submittal log?
The general contractor's project engineer usually maintains it, with input from subcontractors on lead times and from the superintendent on required-on-site dates. The architect often keeps a record of submittals received for review.
Does this submittal log template work in Google Sheets?
Yes. Upload the .xlsx file to Google Drive and open it with Google Sheets. The formulas, drop-downs and color rules carry over. The CSV version imports into Google Sheets, Smartsheet and most project tools.