Free Construction Change Order Template and Log (Excel, Word, PDF)

A construction change order is the signed agreement that changes the contract's scope, price or time. This free template covers the whole path: a pricing sheet that adds markup, bond and insurance to labor, material, equipment and subcontractor costs, a log that follows each change from potential change order to signed change order with a running contract sum, a daily T&M ticket, and a printable change order form for signatures.

Updated . Free to download, no email required.

Download the template

The example rows use a fictional project. Delete them and the template is ready for yours.

What's in the template

  • Change order log: PCO and CO numbers, cause, source document, pricing method, requested and approved amounts and days
  • Contract summary: original contract sum, approved changes, current contract sum, pending exposure and revised completion date
  • Running contract sum after each approved change, and days each request has waited on the owner
  • Pricing sheet: labor, material, equipment and subcontractor lines with markup, bond and insurance
  • Daily T&M ticket for work directed before a price is agreed
  • Word and PDF change order form with contract sum and contract time adjustments and signature block
  • Filled example from a fictional medical office building. Free, no email required

What a working change order log looks like

Seven changes on a fictional $18,450,000 medical office building, as of Nov 20, 2026. Three are signed and move the contract sum to $18,491,150. Two are submitted and waiting on the owner, worth $10,471. PCO-004 has waited 35 days, which is a meeting item. One was rejected and stays in the log with the reason.

Example change order log

Fictional example. Contract sum after counts approved changes only.
CO no.PCO no.TitleCauseMethodRequestedStatusApprovedDaysContract sum afterDays waiting
CO-001PCO-001Add card readers at four exterior doorsOwner requestLump sum$14,200Approved$13,8500$18,463,850
CO-002PCO-002Remove unsuitable soils at building padUnforeseen conditionT&M$38,400Approved$36,9003$18,500,750
CO-003PCO-003Delete vestibule tile upgrade (credit)Value engineeringLump sum-$9,600Approved-$9,6000$18,491,150
PCO-004Lower storm line SD-4 at footing F7Design error or omissionLump sum$8,021Submitted35
PCO-005Reroute supply duct at Level 3 imaging suiteDesign error or omissionLump sumPricing
PCO-006Dedicated circuits for owner exam equipmentOwner requestLump sum$2,450Submitted1
PCO-007Winter protection at Level 1 slabWeatherT&M$11,300Rejected

Example pricing for PCO-004

Fictional example. Use the rates, markups and percentages your contract allows.
LineBasisAmount
Labor32 hours across 3 classifications$2,472.00
MaterialPipe, bedding stone, fittings$2,334.00
EquipmentExcavator and trench box, 1 day$1,425.00
Own work subtotal$6,231.00
Markup on own work15% (example rate)$934.65
Subcontractor workSurvey layout and as-built$650.00
Markup on subcontractor work5% (example rate)$32.50
Subtotal$7,848.15
Bond1.0% of subtotal$78.48
Insurance1.2% of subtotal$94.18
Total requestedRounded to the dollar on the log$8,020.81

PCO, COR and change order: the three stages

Most change order templates are a single form. In practice a change goes through three stages, and losing track of the first two is where money goes missing.

StageWhat it isWhen to create itIn the template
Potential change order (PCO)A possible change that has been identified but not priced or agreed. Some contracts call it a change event or proposed change.The day you learn of it: an RFI answer, ASI, owner request or field condition.A new line in the log with status Identified or Pricing.
Change order request (COR)Your priced proposal to the owner with backup. Also called a change proposal or PCO request.When the pricing is complete, within the time the contract allows.The pricing sheet, then status Submitted with the date and amount.
Change order (CO)The signed modification to the contract sum and contract time.When the owner, architect and contractor sign it.CO number, approved amount, days and date, and the running contract sum updates.

A construction change directive (CCD) sits between the second and third stage. The owner directs the work to proceed before the price is agreed. Log it with its PCO, track the work on daily T&M tickets, and keep pricing it until a change order is signed.

How the pricing sheet adds markup

The pricing sheet separates your own work from subcontracted work because most contracts allow different markups on each. The example prices PCO-004, lowering a storm line that conflicted with a footing:

  1. Own work is labor (hours × rate), material (quantity × unit cost) and equipment.
  2. Markup on own work covers overhead and profit at the contract rate. The example uses 15 percent.
  3. Subcontractor work is the sub's price, with its own markup. The example uses 5 percent.
  4. Bond and insurance are a percentage of the subtotal, if the contract allows them.
  5. Total is what goes on the change order request and the log.

The percentages in the example are placeholders. Overhead and profit limits, allowable labor burden, equipment rate sources and whether bond and insurance are allowed all come from your contract, so set them from the general conditions before you price the first change.

What the change order log tracks

ColumnWhat to enterWhy it matters
CO no. and PCO no.The PCO number when identified. The CO number once signed.One line follows the change through every stage.
Title, cause and sourceWhat changed, why (owner request, design error, unforeseen condition and so on) and the RFI, ASI or CCD behind it.Cause decides who pays. The source is your backup.
Pricing methodLump sum, T&M, unit price, or T&M not to exceed.T&M changes need daily tickets to support the price.
Dates identified and submittedWhen you learned of it and when the request went to the owner.Proves you met the notice period and starts the waiting clock.
Requested amount and daysFrom the pricing sheet.Pending exposure totals every submitted request.
StatusIdentified, Pricing, Submitted, Approved, Rejected or Void.Only Approved moves the contract sum.
Approved amount, days and dateWhat the owner signed.Often less than requested. Keep both.
Contract sum after changeNothing. It calculates.Your pay application's change order total must match it.
Days waiting on ownerNothing. It calculates for submitted changes.Turns red after 21 days, so stale requests reach the meeting.

How to use the template

  1. Enter the contract basics

    Original contract sum and substantial completion date at the top of the log. Set the markup, bond and insurance rates on the pricing sheet from your contract.

  2. Log every potential change on the day

    Even the ones you expect to absorb. A PCO with zero cost is still a record that the issue was raised.

  3. Give notice within the contract period

    Check the notice clause. Late notice is the most common reason a valid change is refused.

  4. Price it with backup

    Fill in the pricing sheet, attach quotes and T&M tickets, and submit. Enter the date and amount in the log.

  5. Chase anything waiting more than three weeks

    Red rows go on the OAC agenda with the amount and the days waiting.

  6. Record the signed change order

    Enter the CO number and approved amount and days. Add the change as its own line on the next pay application's schedule of values.

Time and material tickets

When the owner directs work before a price is agreed, the daily T&M ticket is your evidence. Record each worker, classification and regular and overtime hours, the material with supplier ticket numbers, and the equipment hours. Get the owner's representative to sign it the same day. The signature confirms the work was performed as listed, not that the price is agreed, and that is all you need it to do.

Common change order mistakes

  • Doing the work on a verbal approval. Get at least a signed directive or T&M ticket first.
  • Missing the notice period. Log the change and send written notice when you identify it, not when you finish pricing.
  • One markup for everything. Most contracts set different rates for own work and subcontracted work.
  • Billing pending changes. Only signed change orders go on the pay application unless the contract says otherwise.
  • Deleting rejected changes. Keep them with the reason. The same issue often returns at closeout.
  • Forgetting time. If the change affects the critical path, request the days on the same request.

Catch changes as they happen

Most missed change orders start as an RFI answer, an ASI or an email that nobody connected to cost. A Clevis bot reading the project's correspondence and documents can flag answers that change scope, link them to the RFI and drawing, and keep a working list of potential changes with their dates and status.

Ask it for submitted changes that have waited more than three weeks, or for the backup behind a change order request, and it will cite the records. It can draft the request letter and build the pricing table as an Excel file for you to check. Pricing, notice and signatures stay with your team, and nothing is sent without your approval.

Frequently asked questions

What is a change order in construction?

A change order is a written agreement, signed by the owner and contractor and often the architect, that changes the contract's scope of work, contract sum, contract time, or all three. It is the formal way to add, remove or modify work after the contract is signed.

What should a change order include?

A change order number, a description of the change and its reason, references to the RFI, ASI or directive behind it, the cost with backup, the change in contract sum, the change in contract time, the new contract sum and completion date, and signatures with dates from each party.

What is the difference between a PCO, a COR and a change order?

A potential change order (PCO) is a possible change that has been identified. A change order request (COR) is the priced proposal sent to the owner. A change order (CO) is the signed contract modification. Terms vary by contract, but tracking all three stages is what keeps changes from being lost.

How much markup is allowed on a change order?

Your contract sets it. Many contracts allow one percentage for overhead and profit on the contractor's own work and a lower percentage on subcontracted work, and some cap or exclude bond and insurance. The template uses example rates you should replace with your contract's.

What is a construction change directive?

A construction change directive (CCD) is a written order from the owner, usually signed by the architect, directing a change before the price or time is agreed. The contractor proceeds with the work, tracks the cost, and the parties settle the amount later in a change order.

Should rejected change orders stay in the log?

Yes. Keep rejected and void changes with the date and reason. They show the issue was raised in time, and they explain the history if the same issue comes back.

What happens if work starts before the change order is signed?

You take on the risk of not being paid for it. If work must start, get a signed construction change directive or at least signed daily T&M tickets, give written notice within the contract period, and record it in the change order log.

Does the change order template work in Google Sheets?

Yes. Upload the .xlsx file to Google Drive and open it with Google Sheets. The pricing formulas, running contract sum and drop-down lists carry over. The change order form is also available as a Word file and a PDF.