Free RFI Log Template for Construction (Excel and CSV)

An RFI log is the running list of every request for information on a project: what was asked, who has to answer, when the answer is due, when the work needs it, and whether the answer changes cost or time. This free Excel template tracks all of it, calculates days open and days overdue for you, and comes filled in with a working example so you can see how a well-kept log reads.

Updated . Free to download, no email required.

Download the template

The example rows use a fictional project. Delete them and the template is ready for yours.

What's in the template

  • 22 columns, from RFI number and spec section to response summary and change reference
  • Days open and days overdue calculate from your dates and the status date
  • Overdue rows turn red. A needed-by date within seven days turns amber
  • Summary sheet: open, overdue, average days to answer, cost and schedule exposure, open RFIs by ball in court
  • Drop-down lists for status, priority and ball in court that you can edit
  • Six example RFIs from a fictional medical office building, ready to delete
  • Opens in Excel, Google Sheets, Numbers and LibreOffice. Free, no email required

What a working RFI log looks like

Six RFIs from a fictional four-story medical office building, as of Nov 20, 2026. The workbook has all 22 columns; this view shows the ones a project engineer checks first. RFI-003 is past its response due date and the corridor framing it affects starts in four days, which is exactly what the weekly review should catch.

Fictional example. Days overdue counts from the response due date to the status date.
RFI no.SubjectSpecBall in courtSentResponse dueAnsweredDays openDays overdueStatusCostDays
RFI-001Storm line conflict at footing F733 41 00Civil engineerOct 6, 2026Oct 13, 2026Oct 12, 20266Closed$7,5000
RFI-002Curtain wall embed spacing, Level 208 44 13Structural engineerOct 20, 2026Oct 27, 2026Oct 29, 20269AnsweredNo0
RFI-003Head-of-wall detail at rated corridor07 84 43ArchitectNov 3, 2026Nov 10, 20261710OpenTBD
RFI-004Ceiling height at Level 3 imaging suite09 51 13ArchitectNov 10, 2026Nov 17, 2026103OpenTBD3
RFI-005Power for owner-furnished exam equipment26 05 19OwnerNov 13, 2026Nov 20, 2026Nov 18, 20265Answered$2,4500
RFI-006Paint color at Stair 209 91 23ArchitectNov 17, 2026Nov 24, 20263OpenNo

What each column is for

Every column in the template answers a question someone will ask you later: the owner at the OAC meeting, the architect when a response is late, or your own team at closeout when a change order is disputed. Fill in the first nine the day the RFI goes out.

ColumnWhat to enterWhy it matters
RFI no.The next number in sequence, such as RFI-014. A revised question keeps its number with a suffix (RFI-014.1).Numbers are never reused, so the log is a complete record even when RFIs are voided.
Subject and questionA short subject and a one-line summary of the actual question.The summary is what people scan in a meeting. The full RFI stays in its own document.
Spec section and drawingThe section (07 84 43) and sheet or detail (7/A-601) the question is about.Lets you find every RFI on a system or sheet before a revision or a claim.
Trade and raised byThe trade affected and who raised it: your project engineer, a sub or the superintendent.Shows which trades are generating questions and who to update when the answer comes back.
Ball in courtWho owes the next action: architect, engineer, owner, GC or sub.The column you sort by when you chase. Most late RFIs are late because nobody owned the chase.
PriorityCritical, High or Normal.Critical means work stops or a decision is needed this week.
Date sent and response dueThe date it was issued and the contractual response date.Response due comes from the contract or Division 01 specs. It is the date you can hold the design team to.
Needed byThe date the affected work starts in the schedule.Often earlier than the response due date. This is the date that actually costs you money.
Date answeredThe date a usable response came back.Stops the days-open clock and feeds the average response time.
Days open and days overdueNothing. They calculate.Objective numbers for the meeting instead of impressions.
StatusDraft, Open, Answered, Closed or Void.Answered and Closed are different on purpose. See the status table below.
Cost impact, est. cost, schedule daysYes, No or TBD, then your estimate and days when you have them.An RFI answer that changes the work is a potential change. Capture it here before it gets lost.
Change refThe PCO or change order number the answer led to.Connects the question to the money at closeout.
Response summary and notesOne line on the answer, and chase history.Lets anyone pick up the log without opening every RFI.

Response due versus needed by

Most RFI logs track one date. This one tracks two, because they answer different questions. Response due is the contractual turnaround, usually set in the general conditions or Division 01, and it is the date you can hold the architect or engineer to. Needed by is when the affected work starts in your schedule, and it is the date that costs money if it slips.

In the example, RFI-003 was due back on Nov 10 and the drywall crew needs the answer before corridor framing starts on Nov 24. The first date tells you the design team is late. The second tells you how late is too late. When needed by comes before response due, say so in the RFI itself and ask for an earlier answer, rather than waiting and then claiming a delay.

Status definitions

StatusUse it whenMoves on when
DraftThe question is written but not issued, often waiting for a sub's markup or the superintendent's review.It is sent to the design team.
OpenThe RFI is with the responding party.A usable answer comes back, or the RFI is withdrawn.
AnsweredA response came back, but it has not been distributed, priced or confirmed in the field.The answer is sent to the affected trades and any cost or time effect is logged as a PCO.
ClosedNothing more is needed from anyone.It stays closed. A follow-up question gets a new RFI or a suffix.
VoidThe question was withdrawn, duplicated or answered by another document.Never reuse the number.

Keeping Answered separate from Closed catches the most common gap in RFI tracking: a response that came back, was filed, and never reached the crew doing the work.

How to run the log each week

  1. Log every RFI the day it goes out

    Number, subject, spec section, sheet, ball in court, date sent, response due and needed by. Ten minutes on the day saves an hour of reconstruction later.

  2. Filter to Open and sort by days overdue

    Red rows are past their response due date. Amber needed-by dates mean work starts within seven days.

  3. Chase by ball in court

    Group the overdue items by who owes the answer and send one follow-up per party, listing each RFI, its due date and the work waiting on it.

  4. Process answers the same week

    Enter the date answered and a response summary, send the answer to the affected trades, and mark cost impact. Open a PCO if the answer changes scope.

  5. Bring the summary to the OAC meeting

    Total open, overdue, critical and average days to answer, plus the open RFIs by party. Attach the log to the minutes.

When an RFI answer changes cost or time

An RFI asks for clarification. When the answer adds work, changes a material or resequences the job, it has become a change, even if the response says it is "for clarification only." Mark cost impact Yes or TBD, open a potential change order (PCO) and enter its number in the Change ref column. The change order template picks up from there.

Watch the notice clock. Most contracts require written notice of a change or claim within a set number of days after you learn of it. AIA A201-2017, for example, uses 21 days for claims. A log that ties each RFI to its PCO and dates is the record you will need if the change is disputed. Your contract governs, so check the notice terms at the start of the job.

How to write an RFI that gets a fast answer

  • One question per RFI. Two questions in one RFI usually get one answer.
  • Point to the exact place. Sheet, detail, grid line, room number and spec paragraph.
  • Show the conflict. Attach a marked-up sketch or photo, and quote what the two documents say.
  • Propose a solution. "Lower SD-4 by 2'-0" between MH-3 and MH-4" is faster to approve than "please advise."
  • State the needed-by date and the work affected. The designer can then prioritize.
  • Say whether you expect a cost or time impact. It protects your position and avoids a surprise later.

Common RFI log mistakes

  • Logging only open items. Closed and void RFIs are part of the record. Keep them in the log.
  • No ball-in-court column. Without it, the chase list depends on someone's memory.
  • Closing an RFI when the email arrives. Close it after the answer reaches the field and any change is logged.
  • Typing days open by hand. Calculated columns stay right as the status date moves.
  • Leaving cost impact blank. TBD is an answer. Blank is how changes go unpriced.
  • One log per sub. Keep one project log, with the trade as a column you can filter.

RFI log, RFI form and RFI register

The RFI form is the document you send: the question, references, attachments and the response block. The RFI log is the list that tracks every form through its life. RFI register usually means the same thing as a log; some teams use register for a fuller version with contract and claim fields. This template is a log with the fields that matter for cost, time and follow-up, so most teams will not need a separate register.

Keep the log current without retyping it

The template works on its own. If you would rather not maintain it by hand, a Clevis bot can keep a working RFI list for the project from the emails, drawings, specs and files you give it access to. It can log a new question with the sheet and spec references, track who owes the answer, and flag RFIs that are overdue or blocking upcoming work.

Before a coordination meeting, ask it for the open RFIs with the work waiting on each one and the source for every status. It can produce the list as an Excel file like this one and draft the follow-ups to the design team. Nothing goes out until you approve it, and if your team issues RFIs in another system, that system stays the official record.

Frequently asked questions

What is an RFI log in construction?

An RFI log is a running list of every request for information on a project. Each line records the question, the drawing and spec references, who must answer, the dates sent, due and answered, the status, and any cost or schedule impact. It is how the contractor tracks open questions and proves when answers were requested and received.

What should an RFI log include?

At a minimum: RFI number, subject, spec section and drawing reference, who raised it, ball in court, date sent, response due date, date answered, status, and cost and schedule impact. This template also tracks the date the work needs the answer, days open, days overdue, priority, trade and the change order number the answer led to.

Who maintains the RFI log?

Usually the general contractor's project engineer or project manager keeps the log, because the GC issues most RFIs and tracks them to the design team. The architect often keeps a parallel log of RFIs received. Agree at the preconstruction meeting whose log is the reference for the OAC meeting.

How long should an RFI response take?

The contract or the Division 01 specifications set the response time. Many projects use 7 to 14 calendar days. If your documents are silent, agree on a turnaround at the preconstruction meeting, and state an earlier needed-by date on any RFI that is holding up work.

What does ball in court mean on an RFI?

Ball in court is the party who owes the next action on the RFI. While the architect is reviewing, the ball is in the architect's court. If the architect asks the contractor for more information, it moves back to the contractor. Sorting the log by ball in court turns it into a chase list.

When can you close an RFI?

Close it when a usable answer has been received, distributed to the trades doing the work, and any cost or schedule effect has been logged as a potential change order. Until then, mark it Answered. Never delete an RFI or reuse its number.

Can an RFI turn into a change order?

Yes. If the answer adds work, changes materials or affects the sequence, it is a change to the contract. Open a potential change order, give written notice within the contract's notice period, and record the PCO number in the RFI log so the two stay connected.

Does this RFI log template work in Google Sheets?

Yes. Upload the .xlsx to Google Drive and open it with Google Sheets. The formulas, drop-down lists and conditional formatting carry over. You can also import the CSV file into Google Sheets, Smartsheet or most project management tools.

Is the template really free?

Yes. Download it without an email address and change it however you like. It includes a filled-in example from a fictional project so you can see how the columns work before you delete the example rows.