Course outline
Running projects with Clevis
Keeping RFIs, submittals, and the schedule moving
Use bots to organize open items, prepare follow-ups, and connect outstanding answers to upcoming work.
7 min read
An RFI list becomes more useful when it shows the work waiting on each answer. At Westbrook Medical, RFI 214 concerns ceiling supports, the ceiling submittal is back for revision, and corridor rough-in is in the next lookahead. Dana asks her bot to bring those records together before the coordination meeting, with the source and the next response needed for each item.
Keep working records and official records clear
Native records in Clevis are the bot's project working records. It can log an RFI, organize a submittal, or update a task as part of the work, without a default approval card. Those records help it track the discussion and prepare the next review. They do not automatically represent the status in Autodesk Construction Cloud or another connected system.
If your team manages RFIs in Autodesk Construction Cloud, that system stays the source of truth for the RFI's official status and response. Ask the bot to name the system and link the matching record when it reports that status. A note in Clevis saying "response received" should not be presented as proof that the official RFI was answered or closed.
Log the question and chase the right person
For RFI 214, ask the bot to keep a working summary with the open question, the related sheet, the party expected to respond, and the activity waiting on it. Ask it to distinguish the contractual response date, any requested earlier answer, and a date inferred from the lookahead. Those dates may serve different purposes.
Before chasing, have it read the latest response. A late item might be waiting on the designer, on a subcontractor's missing information, or on your own review. The follow-up should ask for the actual missing piece. Sending that message outside the team waits for your approval; updating the bot's Clevis working summary can happen during the task.
Track the next submittal step
A submittal marked overdue is not enough information for a useful chase. Find whether it has yet to arrive, is in review, or was returned for revision. At Westbrook, a revised ceiling support package is still owed by the subcontractor, while the lighting package is already with the reviewer. Asking both subcontractors to "submit immediately" would misstate one of them.
Westbrook · Example submittal log
3 items to review
09 51 00-02 · Ceiling support package
Returned for revision
Next: Revised support information from the ceiling subcontractor
Example: revised package requested by Thursday
26 51 00-01 · Lighting fixtures
In review
Next: Review response from the electrical engineer
Example: review response needed by Friday
23 37 13-01 · Diffusers and grilles
Not yet submitted
Next: Initial package from the mechanical subcontractor
Example: package requested by Wednesday
Check the matching record in the connected system before reporting an official status. Outward chases wait for approval.
Ask for the item number, spec section, current source status, next party, and what is needed. For anything tied to procurement, ask which record supports the required date. A reviewed submittal is not evidence that the purchase order was placed, fabrication started, or delivery was confirmed.
Turn open items into a lookahead
Use a dated schedule or lookahead and give the bot a period to review. Dana asks, "For next week's east corridor work, list activities with unresolved RFIs or submittals. Show the dependency and cite the records." The answer should separate a recorded relationship from a possible constraint that the superintendent needs to confirm.
- Check the schedule date. A useful lookahead starts with the version the team is using.
- Ask what changed. Compare the new answer with the last coordination review, including items that were resolved.
- Keep missing links visible. If no activity is tied to an RFI, ask who can confirm the effect rather than accepting an invented dependency.
- Prepare decisions. Finish with questions for the meeting and draft follow-ups for review.
The bot can gather evidence and suggest where a missing answer may affect the sequence. It should not declare a delay or move a committed milestone on that basis alone. Dana and the superintendent review the constraint, decide the coordination response, and approve any update that will be written to the connected system.
Check your understanding
Optional1. A bot logs an RFI working record in Clevis. What does that establish?
2. A lighting submittal is with the reviewer. What should the chase identify?
3. An RFI may affect rough-in, but no schedule dependency is recorded. What should the answer say?