Free OAC Meeting Minutes Template (Word and PDF) With Agenda
OAC meeting minutes are the written record of the regular owner-architect-contractor meeting: who attended, what was discussed, what was decided, and who owes each action by when. This free Word template gives you a standing agenda, a numbering system that carries open items forward until they close, and sections for RFIs, submittals and changes, plus a fully filled example from a fictional project.
Download the template
- WordOAC minutes templateWord. Blank, with the standing agenda and guidance. 40 KBDownload OAC minutes template (Word)
- PDFOAC minutes templatePDF. Printable blank. 249 KBDownload OAC minutes template (PDF)
- WordFilled example minutesWord. Meeting 14 on a fictional project. 40 KBDownload Filled example minutes (Word)
- PDFFilled example minutesPDF. 256 KBDownload Filled example minutes (PDF)
The example rows use a fictional project. Delete them and the template is ready for yours.
What's in the template
- Header block: project, meeting number, date, location, prepared by, next meeting and distribution
- Attendance table by company and role
- Standing agenda: safety, previous minutes, schedule, old business, RFIs, submittals, changes and cost, quality, owner items, design team items, new business
- Meeting.item numbering that keeps open items on the agenda until they close
- Item, discussion, type, responsible, due and status columns in every section
- Action item list and a correction-window statement
- A fully filled example of meeting 14 on a fictional medical office building. Free, no email required
What good OAC minutes look like
Meeting No. 14, Wednesday, Nov 19, 2026, on a fictional medical office building. Every open item has an owner and a date. Item 11.04 is in its third meeting, which is visible from its number alone. The RFI, submittal and change items come straight from the logs, so the minutes and the logs never disagree.
Example attendance
| Name | Company | Role | Attendance |
|---|---|---|---|
| Priya Raman | Harbor Point Health (owner) | Owner's project manager | Present |
| Marcus Hale | Example Architects | Project architect | Present |
| Lena Ortiz | Example Builders (GC) | Project manager | Present |
| Sam Whitaker | Example Builders (GC) | Superintendent | Present |
| Jordan Kim | Example Builders (GC) | Project engineer (minutes) | Present |
| Dev Patel | Example MEP Engineers | Mechanical engineer | Joined by video for item 14.06 |
| Ana Flores | Example Structural | Structural engineer | Absent |
Example minutes, meeting 14
| Item | Topic | Discussion | Responsible | Due | Status |
|---|---|---|---|---|---|
| 14.01 | Safety | No recordable incidents since meeting 13. Steel erection is complete; fall protection focus moves to curtain wall install on Level 2. | |||
| 14.02 | Previous minutes | Minutes of meeting 13 accepted with one correction: item 13.07 due date is Nov 21, not Nov 14. | |||
| 14.03 | Schedule | Structural steel topped out Nov 13, two days ahead of the baseline. Curtain wall install starts Feb 15 if the resubmittal is approved by Dec 1. Critical path runs through curtain wall, then interior framing on Levels 2 and 3. | |||
| 14.04 | Schedule | Three-week lookahead attached. Level 2 corridor framing starts Nov 24 and needs the RFI-003 answer. | Architect | Nov 21 | Open |
| 11.04 | Old business (carried) | Owner to confirm imaging equipment vendor so the Level 3 slab penetrations can be laid out. | Owner | Nov 26 | Open. Third meeting carried. |
| 13.07 | Old business (carried) | Architect to issue revised door hardware schedule. | Architect | Nov 21 | Open |
| 13.09 | Old business (carried) | GC to submit PCO-004 backup with surveyor invoice. | GC | Nov 12 | Closed. Sent Nov 11. |
| 14.05 | RFIs | RFI-003 (rated head-of-wall at corridor) is 9 days past its response due date. Framing starts Nov 24. Architect will answer by Nov 21. | Architect | Nov 21 | Open |
| 14.06 | RFIs | RFI-004 (duct conflict at imaging suite ceiling). Mechanical engineer reviewing a reroute; architect prefers keeping the 10'-0" ceiling. Decision needed by Dec 1. | Architect / MEP engineer | Nov 26 | Open |
| 14.07 | Submittals | Curtain wall resubmittal (08 44 13-001 Rev 1) received by architect Nov 17. GC asked for a 7-day review because float is gone. Architect agreed to Nov 24. | Architect | Nov 24 | Open |
| 14.08 | Submittals | Panelboards (26 24 16-001) in review 38 days, 24 days past due. Engineer to return by Nov 23. | MEP engineer | Nov 23 | Open |
| 14.09 | Submittals | AHU product data (23 73 13-001) not yet received from the mechanical sub; it was due Oct 21 for a Mar 1 delivery. Sub promises Nov 24. GC to report the delivery risk at meeting 15. | GC | Dec 3 | Open |
| 14.10 | Changes and cost | PCO-004 (lower storm line, $8,021) submitted Oct 16, 34 days without a response. Owner to respond by Nov 26. | Owner | Nov 26 | Open |
| 14.11 | Changes and cost | PCO-006 (exam room circuits, $2,450) submitted Nov 19. Owner reviewing. | |||
| 14.12 | Changes and cost | PCO-007 (winter protection) rejected Nov 14. GC accepts; it will stay in the log as rejected. | |||
| 14.13 | Owner items | Owner asked for a monthly photo report for the board starting December. | GC | Dec 5 | Open |
| 14.14 | New business | Pay application 6 pencil draft due Nov 25. Architect walk-through Nov 26 at 9:00. | GC | Nov 25 | Open |
What an OAC meeting is for
The OAC meeting is the regular meeting between the owner, the architect and the general contractor, usually weekly or every other week during construction. Consultants and key subcontractors join for the items that concern them. It is where decisions that need the owner or the design team get made: answers on late RFIs, review of critical submittals, approval of changes, and schedule risks that need someone outside the GC to act.
It is not the place for trade coordination or field means and methods. Keep those in the GC's own subcontractor meeting. An item belongs on the OAC agenda if it needs an owner or design decision, or if it affects cost, time or the design.
A standing OAC agenda
Use the same order every meeting so people know where to find things. The template is built on this agenda:
| Section | What to cover |
|---|---|
| 1. Safety | Incidents since the last meeting, upcoming high-risk work, logistics changes. |
| 2. Previous minutes | Corrections received, then accept the previous minutes. |
| 3. Schedule | Progress against the baseline, critical path, three-week lookahead, milestones at risk. |
| 4. Old business | Every open item from previous meetings, with its original number. |
| 5. RFIs | Overdue and critical RFIs and answers needed before upcoming work. Attach the RFI log. |
| 6. Submittals | Items late from subs, items past review due, resubmittals and long-lead releases. Attach the submittal log. |
| 7. Changes and cost | Change requests waiting on the owner, directives, allowances and contingency. |
| 8. Quality and inspections | Inspections, test results, deficiencies, mock-ups. |
| 9. Owner items | Owner decisions, owner-furnished equipment, move-in planning. |
| 10. Design team items | ASIs, bulletins and clarifications in progress. |
| 11. New business | Anything new. It gets the next number and becomes old business if it stays open. |
| 12. Action items and next meeting | The full list of open actions with owners and dates, and the next meeting date. |
Send the agenda a day or two ahead. The previous minutes' open items are most of the next agenda, so issuing minutes quickly does double duty.
Numbering items so nothing drops
Number every item meeting.item: 14.05 is the fifth item of meeting 14. When an item stays open, it keeps its original number in every later set of minutes, under old business, until it is closed. Then it is marked closed once and drops off.
The number tells everyone how long an issue has been open without anyone saying it. In the example, 11.04, the owner's imaging equipment vendor, is in its third meeting, and the number alone makes the point. Never renumber an open item, and never delete one. Close it with a date and a note.
How to write minutes people act on
- Record decisions and actions, not conversation. One or two sentences per item: what was decided or what is needed.
- Every action gets one responsible party and a date. "Architect to answer RFI-003 by Nov 21" can be chased. "Team to review" cannot.
- Use the numbers from the logs. RFI-003, PCO-004 and 26 24 16-001 tie the minutes to the records.
- Mark the type. Info, Action or Decision, so the action list builds itself.
- State facts the logs prove. "In review 38 days, 24 past due" is harder to argue with than "overdue."
- Issue within 24 to 48 hours while people still remember the meeting.
Who writes the minutes, and how corrections work
Either the general contractor or the architect writes the minutes, depending on the contract and the specs. On most commercial projects the GC runs the meeting and its project engineer or project manager takes the minutes. Settle it at the preconstruction meeting.
End every set of minutes with a correction window, for example: written corrections within five business days of distribution, after which the minutes stand as written. Review corrections at the start of the next meeting. Minutes are a strong record of what was said, but they do not change the contract. A change in cost or time still needs a signed change order.
Common OAC minutes mistakes
- Starting fresh each meeting. Open items vanish. Carry them under old business until closed.
- Actions with no name or date.
- Transcript-style minutes. Nobody reads them, and the decisions get lost.
- Status from memory. Pull RFI, submittal and change status from the logs before the meeting.
- Late distribution. Minutes sent a week later are already out of date.
- No distribution list. Record who received them, including people who were absent.
From meeting notes to minutes
Give a Clevis bot your notes or the meeting transcript and it can draft minutes in this format, carrying forward the open items from the last meeting with their original numbers. Before the meeting, it can build the RFI, submittal and change sections from the project records you have connected, with the source for each status.
It can produce the draft as a Word document for you to edit. You review and correct it, and it is only sent to the distribution list when you approve.
Frequently asked questions
What does OAC stand for in construction?
OAC stands for owner, architect and contractor. An OAC meeting is the regular project meeting between those three parties, with consultants and subcontractors joining as needed.
What should be included in OAC meeting minutes?
The project and meeting number, date, location, attendees, who prepared the minutes and the distribution list, then numbered items for safety, previous minutes, schedule, old business, RFIs, submittals, changes and cost, quality, owner and design items and new business. Each action item needs a responsible party and a due date. End with the next meeting date and a correction window.
How often are OAC meetings held?
Usually weekly or every two weeks during construction, more often during critical phases and less often during preconstruction. The contract or Division 01 specs often set the frequency.
Who runs the OAC meeting and takes the minutes?
On most commercial projects the general contractor's project manager runs the meeting and the GC prepares the minutes. Some contracts give the architect that role. Agree on it at the preconstruction meeting.
How should OAC meeting items be numbered?
Use meeting.item numbering, such as 14.05 for item 5 of meeting 14. Open items keep their original number in later minutes until they are closed, which shows how long each issue has been open.
How soon should OAC minutes be distributed?
Within 24 to 48 hours of the meeting is a common standard. Include a window, such as five business days, for written corrections, after which the minutes stand as written.
What is the difference between an OAC meeting and a subcontractor meeting?
The OAC meeting covers decisions that need the owner or the design team, such as late RFIs, critical submittals, changes and schedule risks. The subcontractor or foremen's meeting covers trade coordination, sequencing and site logistics, and is run by the GC.
Is there a free OAC meeting agenda template?
Yes. The blank template on this page is built on the standing agenda, so the same file works as the agenda before the meeting and the minutes after it.