Pay Application Checklist for Contractors (Free Excel, Word and PDF)
A construction pay application is a package, not a single form: the application and schedule of values, approved change orders, stored material backup, lien waivers and whatever else the contract requires. This free checklist lists 43 items across first, progress and final applications and the GC's review of subcontractor pay apps. The Excel version also calculates retainage and the current payment due from your schedule of values.
Download the template
- ExcelPay application workbookExcel. Checklist, amount due, schedule of values, sub tracker. 17 KBDownload Pay application workbook (Excel)
- WordPrintable checklistWord. Tick boxes for every item. 39 KBDownload Printable checklist (Word)
- PDFPrintable checklistPDF. 158 KBDownload Printable checklist (PDF)
The example rows use a fictional project. Delete them and the template is ready for yours.
What's in the template
- 43 checklist items in eight groups, each marked for all applications, the first, the final, stored materials or GC review
- Status drop-down (Ready, Missing, N/A) with a running count. Missing items turn red
- Amount due summary: contract sum to date, completed and stored, retainage, previous certificates, current payment due and balance to finish
- Schedule of values with percent complete, balance to finish and retainage per line, and change orders on their own lines
- Subcontractor pay app tracker for waivers, insurance certificates and certified payroll
- Filled example from a fictional medical office building. Free, no email required
The amount-due math, worked through
Application 6 on a fictional medical office building with 5 percent retainage. Every number on the summary comes from the schedule of values below it, which is how the workbook is built: you update the schedule of values and the summary follows.
Example application summary
| Line | Amount |
|---|---|
| 1. Original contract sum | $18,450,000.00 |
| 2. Net change by approved change orders | $41,150.00 |
| 3. Contract sum to date | $18,491,150.00 |
| 4. Total completed and stored to date | $7,326,150.00 |
| 5. Retainage (5%) | $366,307.50 |
| 6. Total earned less retainage | $6,959,842.50 |
| 7. Less previous certificates for payment | $5,355,435.00 |
| 8. Current payment due | $1,604,407.50 |
| 9. Balance to finish, including retainage | $11,531,307.50 |
Example schedule of values
| Item | Description | Scheduled value | Previous | This period | Stored | Total to date | % | Retainage |
|---|---|---|---|---|---|---|---|---|
| 1 | General conditions | $1,420,000 | $520,000 | $72,000 | $592,000 | 42% | $29,600 | |
| 2 | Sitework and utilities | $1,850,000 | $1,620,000 | $140,000 | $1,760,000 | 95% | $88,000 | |
| 3 | Concrete | $2,380,000 | $1,690,000 | $310,000 | $2,000,000 | 84% | $100,000 | |
| 4 | Structural steel | $2,150,000 | $1,200,000 | $410,000 | $1,610,000 | 75% | $80,500 | |
| 5 | Building envelope | $2,960,000 | $180,000 | $165,000 | $245,000 | $590,000 | 20% | $29,500 |
| 6 | Interiors | $3,240,000 | $0 | $48,000 | $48,000 | 1% | $2,400 | |
| 7 | Mechanical and plumbing | $2,890,000 | $260,000 | $190,000 | $450,000 | 16% | $22,500 | |
| 8 | Electrical | $1,560,000 | $140,000 | $95,000 | $235,000 | 15% | $11,750 | |
| CO-001 | Card readers at exterior doors | $13,850 | $0 | $13,850 | $13,850 | 100% | $692 | |
| CO-002 | Unsuitable soils removal | $36,900 | $36,900 | $0 | $36,900 | 100% | $1,845 | |
| CO-003 | Vestibule tile credit | -$9,600 | -$9,600 | $0 | -$9,600 | 100% | -$480 |
The pay application checklist
Mark the items your contract does not require as N/A at the start of the job, then use the rest every month. Items labelled First, Final or Stored materials apply only to those applications. The GC review group is for checking subcontractor pay apps before you roll them into yours.
Before you start
- Read the payment terms: period end date, submission deadline, format, who certifies (architect, owner's rep, lender) and payment due date
- Confirm whether the owner wants a pencil draft (pencil requisition) before the formal application, and its deadline
- Make sure the schedule of values was approved by the owner or architect before the first billing (First)
- Collect the approved change order list and confirm which ones are fully executed
Application form and schedule of values
- Use the form the contract requires (AIA G702/G703, ConsensusDocs 710, or the owner's or lender's own form)
- Every SOV line shows scheduled value, previous work completed, work this period, materials stored, total to date, percent complete, balance to finish and retainage
- Percent complete matches field progress: walk the job or review it line by line with the superintendent
- No line is billed above 100 percent, and early lines are not front-loaded beyond what the owner accepted
- Previous application amounts match the last certified application, not the last one you submitted
- Totals on the continuation sheet tie to the summary page
- Approved change orders appear as their own SOV lines; pending or unsigned changes are not billed unless the contract allows it
- Retainage is calculated at the contract rate, and any reduction (for example at 50 percent complete) is approved in writing
Stored materials
- Supplier invoices or bills of sale for every stored material line (Stored materials)
- Photos and storage location; off-site storage approved by the owner in writing (Stored materials)
- Proof of insurance covering the stored materials and, if required, title transfer to the owner (Stored materials)
- Stored materials billed in a previous period are moved to work completed when installed, not billed twice (Stored materials)
Lien waivers and releases
- Your conditional waiver for the amount of this application
- Your unconditional waiver for the payment received last period
- Subcontractor and supplier waivers: conditional for this period, unconditional for amounts already paid to them
- Waivers on the statutory form where your state requires one, signed and notarized if required
- Waiver amounts and through-dates match the application
Compliance and backup
- Certificates of insurance current for you and for subcontractors on site
- Certified payroll for the period on prevailing wage or Davis-Bacon work
- Updated schedule or narrative, daily reports or photos, if the contract asks for them
- Subcontractor pay applications as backup for your SOV lines, if required
- Sworn statement or contractor's affidavit listing subs, suppliers and amounts, if the lender or title company requires it
- Joint check agreements noted on the application
Final application
- Certificate of substantial completion and punch list sign-off (Final)
- Request for release of retainage (Final)
- Final unconditional waivers from every subcontractor and supplier (Final)
- Consent of surety to final payment on bonded projects (Final)
- Closeout documents delivered: as-builts, O&M manuals, warranties, attic stock and training sign-offs (Final)
- Final affidavits and releases required by the contract (for example, debts and claims paid) (Final)
- Certificate of occupancy, if payment is tied to it (Final)
Reviewing subcontractor pay applications (GC)
- Billing matches the subcontract SOV and approved change orders (GC review)
- Percent complete checked with the superintendent (GC review)
- Retainage withheld at the subcontract rate (GC review)
- Conditional waiver for this period and unconditional waiver for the last payment received (GC review)
- Insurance certificate and license current (GC review)
- Back-charges deducted only with written notice under the subcontract (GC review)
Submit and follow up
- Signed, and notarized if required
- Submitted by the deadline, to every required recipient, by the required method
- Track the certification date, amount certified and expected payment date; follow up under the prompt payment terms if it is late
How the amount due is calculated
The summary follows the same order as the standard application forms, so it lines up with an AIA G702, a ConsensusDocs 710 or most owner forms:
- Contract sum to date = original contract sum + net approved change orders.
- Total completed and stored = work completed in previous applications + work this period + materials presently stored.
- Retainage = completed and stored × the retainage rate (the contract may set different rates for work and stored materials, or reduce retainage after a milestone).
- Total earned less retainage = total completed and stored − retainage.
- Current payment due = total earned less retainage − previous certificates for payment.
- Balance to finish, including retainage = contract sum to date − total earned less retainage.
The line that causes the most rejections is previous certificates. Use the total the architect or owner actually certified on earlier applications, not what you requested. If application 5 was certified for less than you asked, carrying your requested figure forward makes this month's math wrong.
First, progress and final applications
| Application | What is different | Watch for |
|---|---|---|
| First | The schedule of values has to be approved before you can bill against it. Many owners also want insurance certificates, bonds and a subcontractor list. | Front-loading. Owners and lenders look closely at early lines such as mobilization and general conditions. |
| Progress | The monthly cycle: percent complete per line, stored materials, signed change orders, conditional waivers for this period and unconditional waivers for the last. | Previous certificates that do not match what was actually certified, and pending changes billed too early. |
| Final | Release of retainage and closeout: substantial completion, punch list, final waivers from everyone, consent of surety, as-builts, O&M manuals and warranties. | One missing sub waiver or closeout document can hold the whole retainage payment. |
Which lien waivers go with each application
Lien waivers come in four kinds: conditional or unconditional, and progress or final. A conditional waiver takes effect only when the payment clears, so it is safe to send before you are paid. An unconditional waiver takes effect when signed, so send it only for money you have already received.
A typical progress application includes your conditional progress waiver for this month's amount and your unconditional progress waiver for last month's payment, plus the same pair from each subcontractor and supplier paid from that money. The final application swaps in final waivers. About a dozen states require their own statutory waiver forms, including California, Texas, Florida and Georgia, and a waiver on the wrong form may not be valid. Check your state's rules and your contract before you use a generic form.
Billing for stored materials
Materials delivered but not yet installed can usually be billed if the contract allows it. Expect to provide the supplier invoice or bill of sale, photos, the storage location and proof that the materials are insured. Off-site storage normally needs the owner's written approval and sometimes a bonded warehouse. In the example, curtain wall units worth $245,000 are stored on site under the building envelope line. When they are installed, they move from stored to completed work, and they must not be billed twice.
Reviewing subcontractor pay applications
A general contractor's application is only as complete as its subcontractors' applications. Collect them several days before your own deadline. Check each one against the subcontract schedule of values and approved change orders, confirm percent complete with the superintendent, withhold retainage at the subcontract rate, and confirm waivers, insurance and certified payroll. The Sub Pay App Tracker sheet shows at a glance which subcontractors still owe something.
Common reasons pay applications are returned
- Percent complete the architect cannot see in the field. Walk the job before you bill, and keep photos.
- Previous application totals that do not match the last certificate.
- Unsigned change orders billed as approved.
- Missing, wrong-form or mismatched lien waivers. Amounts and through-dates must match the application.
- Stored materials without invoices, insurance or approval.
- Retainage reduced without written approval.
- Late submission. Missing the cutoff can push payment a full month.
Assemble the package without the scramble
A Clevis bot can read the payment terms in your contract and turn them into the checklist for your project, so N/A items are settled once instead of every month. Each cycle, it can check which subcontractor waivers, insurance certificates and backup documents are in the files you have connected and list what is still missing.
It can also compare this month's schedule of values against the signed change orders and the last certified application and point out lines that do not tie. You keep control of the billing, the certification and anything sent to the owner or lender.
Frequently asked questions
What documents are included in a construction pay application?
Usually the application form, the schedule of values or continuation sheet, approved change orders, lien waivers from you and your subcontractors and suppliers, stored material backup if you are billing for stored materials, and anything else the contract requires, such as certified payroll, insurance certificates, updated schedules or a sworn statement.
How is retainage calculated on a pay application?
Multiply the total completed and stored to date by the retainage rate in the contract, often 5 or 10 percent. Some contracts use different rates for completed work and stored materials, or reduce retainage after the project reaches a milestone such as 50 percent complete. Retainage is released with the final application.
What is the difference between conditional and unconditional lien waivers?
A conditional waiver only takes effect once the payment is received, so you can submit it with an application before you are paid. An unconditional waiver takes effect when signed, so it should only be given for payments already received. Progress applications typically include a conditional waiver for this period and an unconditional waiver for the last payment.
What is a schedule of values?
A schedule of values breaks the contract sum into line items, such as general conditions, sitework, concrete and electrical, each with a scheduled value. Each month you bill the percentage of each line that is complete. The owner or architect approves it before the first application.
What is a pencil draft?
A pencil draft, or pencil requisition, is a preliminary version of the pay application reviewed with the owner or architect before the formal submission. Agreeing on percent complete in the draft avoids a rejected application and a delayed payment.
Can contractors bill for stored materials?
Often yes, if the contract allows it. Expect to provide invoices or bills of sale, photos, the storage location and proof of insurance, and to get written approval for materials stored off site.
What extra documents does a final pay application need?
Typically a certificate of substantial completion, punch list sign-off, final unconditional waivers from every subcontractor and supplier, consent of surety on bonded jobs, closeout documents such as as-builts, O&M manuals and warranties, and any final affidavits the contract requires.
Is this an AIA G702 form?
No. AIA G702 and G703 are copyrighted documents you license from AIA. This template follows the same standard application math so it lines up with G702, ConsensusDocs 710 and most owner forms, and it is free to use as a checklist and calculator alongside the form your contract requires.